Most residential planning permit applications in Melbourne take between four and nine months from lodgement to a decision. More complex proposals, those involving heritage overlays, third-party objections, referral authority involvement, or contentious neighbourhood character issues, regularly take twelve months or longer. At VCAT, contested applications can add another six to twelve months on top of that.
The statutory figure you will see quoted everywhere, 60 days, is the timeframe within which council is required to make a decision under the Planning and Environment Act 1987. In practice, the 60-day clock is regularly paused by Requests for Further Information (RFIs), advertising periods, and referral processes. It is a legal minimum, not a reliable project planning timeline.
SilverPoint Building Designers & Planning Consultants has been guiding projects through Melbourne's planning system for over 40 years and 1,800+ completed applications.
This page gives you an honest account of what the timeframes actually look like, what drives delays, and where the real variables are.