What is a Planning Permit?

Most residential planning permit applications in Melbourne take between four and nine months from lodgement to a decision. More complex proposals, those involving heritage overlays, third-party objections, referral authority involvement, or contentious neighbourhood character issues, regularly take twelve months or longer. At VCAT, contested applications can add another six to twelve months on top of that. 

The statutory figure you will see quoted everywhere, 60 days, is the timeframe within which council is required to make a decision under the Planning and Environment Act 1987. In practice, the 60-day clock is regularly paused by Requests for Further Information (RFIs), advertising periods, and referral processes. It is a legal minimum, not a reliable project planning timeline. 

SilverPoint Building Designers & Planning Consultants has been guiding projects through Melbourne's planning system for over 40 years and 1,800+ completed applications.  

This page gives you an honest account of what the timeframes actually look like, what drives delays, and where the real variables are.

Building Design Yarra

What the 60-Day Rule Means

The Planning and Environment Act 1987 sets a 60-day statutory timeframe for councils to decide on most planning permit applications. In theory, a well-prepared standard application should receive a decision within roughly three months of lodgement. 

Here is what suspends the 60-day clock and why real-world timelines almost always run longer:  

  •  Advertising (notification period) 

When an application must be publicly notified, which applies to the majority of residential development applications, a mandatory 14-day advertising period runs. During this period, the time is paused. Any objections received add further time for a council hearing and officer deliberation. 

  •  Requests for Further Information (RFI) 

If council requires additional documentation, additional drawings, a heritage assessment, or a traffic impact report, the clock stops until that information is provided. The quality and completeness of the original application directly determines whether an RFI is issued. A well-prepared submission significantly reduces this risk. 

  •  Referral authorities 

Applications involving properties near major roads, waterways, or vegetation overlays are referred to external authorities, VicRoads, Melbourne Water, the Country Fire Authority, or Parks Victoria. Each referral authority has its own response period. The 60-day clock is paused while referrals are outstanding. 

  •  Internal council workload 

Councils with high application volumes, particularly inner-city councils, process applications more slowly in practice, regardless of the statutory timeframe. A statutory 60-day obligation does not prevent a six-month queue. 

 

Town Planning Process

What Actually Determines Your Timeline?

No two applications have the same timeline. The following factors are the primary determinants of how long your specific application will take: 

  • Application completeness at lodgement - Incomplete applications almost always receive an RFI, pausing the statutory clock and adding weeks or months. A complete, well-documented submission is the single most controllable factor in your timeline. 
  • Council workload and officer availability - Inner-city and prestigious inner-east councils (Boroondara, Stonnington, Port Phillip) typically have higher application volumes and more rigorous assessment processes. Outer suburban councils process applications faster. 
  • Whether advertising is required - Applications requiring public notification add a minimum of 14 days plus any objection-handling time. 
  • Number and strength of objections - Each objection must be considered. If there are multiple objectors, council may schedule a meeting. Sustained objections increase the likelihood of VCAT involvement. 
  • Referral authority requirements - VicRoads, Melbourne Water, and other referral authorities each introduce their own timeframes. 
  • Property overlays - Heritage Overlays, Environmental Significance Overlays, and Significant Landscape Overlays trigger additional assessment criteria and often require specialist reports. 
  • Complexity of the proposal - A rear extension on an unremarkable residential lot moves faster than a four-lot townhouse development in a Design and Development Overlay area. 
  • VCAT appeals - If a permit is refused or granted over objections, any party can appeal to the Victorian Civil and Administrative Tribunal. VCAT hearings commonly take six to twelve months to resolve from the point of referral. 
Home Extention Port Phillip

VicSmart - When You Can Get a Decision in 10 Business Days

VicSmart is Victoria's fast-track planning permit pathway for lower-complexity applications. Eligible VicSmart applications are assessed within 10 business days, require no public advertising, and carry no third-party objection rights. For qualifying projects, VicSmart reduces months of uncertainty to roughly two weeks. 

Amendment VC288 - The 2025 expansion that changed dual occupancy timelines 

In October 2025, Amendment VC288 expanded VicSmart eligibility to include dual occupancy developments (two dwellings on a lot) and two-lot subdivisions, previously among the most time-consuming permit types in the system. Under VC288, these applications can now qualify for the 10-day VicSmart pathway, provided: 

  • The site is in an eligible residential zone (GRZ, NRZ, RGZ, MRZ, TZ - the Low Density Residential Zone is excluded) 
  • The proposal fully complies with all Clause 55 (ResCode) standards, including setbacks, heights, site coverage, solar access, and overlooking controls 
  • No overlay exclusions apply - Heritage Overlays, Bushfire Management Overlays, Environmental Audit Overlays, and Neighbourhood Character Overlays generally remove VicSmart eligibility 
  • All other VicSmart criteria under Clause 71.06 are met 

For sites that qualify, VC288 effectively removes the months-long planning timeline from dual occupancy development. For sites that do not qualify, particularly those in Heritage Overlay areas or with non-compliant designs, the standard process applies. 

SilverPoint Building Designers and Planning Consultants assess VicSmart eligibility as part of every dual occupancy and subdivision feasibility assessment. If your site qualifies, we will tell you, and structure the application to stay within the pathway. 

Other common VicSmart-eligible applications include: carports and garages, small additions, single dwellings on lots under specified areas, minor signage, and certain vegetation removal applications.

Town Planning Stonnington

Which Melbourne Councils Are Faster and Which Take Longer?

Timeframes vary significantly across Melbourne's 31 councils. The following gives a general indication based on application volumes, internal processes, and the complexity of planning schemes: 

Typically faster (3–5 months for standard residential applications): 

Whittlesea, Melton, Wyndham, Casey, Cardinia, outer growth corridor councils with high housing volumes and streamlined processes, lower overlay complexity. 

Mid-range (4–7 months): 

Knox, Manningham, Maroondah, Whitehorse, Monash, well-established eastern suburbs councils with moderate overlay complexity and consistent processing times. 

Typically slower (6–12+ months for complex applications): 

Boroondara, Stonnington, Port Phillip, Melbourne, Yarra, inner-city and inner-east councils with dense heritage overlay coverage, higher application scrutiny, and greater likelihood of third-party objections. 

Note: These are indicative ranges based on typical applications. The complexity of your specific proposal, the completeness of your application, and council workload at any given time will affect your actual outcome. A simple application in Boroondara can move faster than a complex one in Whittlesea.  

7

What SilverPoint Building Designers & Planning Consultants Does Differently to Reduce Delays

The single most controllable variable in any planning timeline is the quality of the application lodged. A well-prepared, council-specific submission with complete documentation reduces RFI risk, supports smoother advertising, and gives the assessing officer everything they need to write a recommendation. 

SilverPoint Building Designers & Planning Consultants reduces planning timelines through: 

Pre-application engagement - For complex applications or those in challenging council areas, SilverPoint arranges pre-application meetings with council officers. A well-targeted pre-application meeting surfaces potential issues before lodgement, not after, and demonstrates to council that the application is prepared by someone who understands their scheme.

Complete first submissions - Every SilverPoint application is reviewed against council's specific planning scheme, overlay controls, and known assessment criteria before lodgement. This is not a generic checklist. It is a submission built for the specific council's expectations. 

Proactive RFI responses - When councils do issue RFIs, SilverPoint responds quickly with complete and targeted documentation. Delayed or partial RFI responses are one of the most common causes of avoidable extended timeframes. 

Council relationships built over 40 years - Knowing how particular councils assess particular application types and what information they need to approve confidently comes from decades of direct experience inside these schemes. 

Frequently Asked Questions about Town Planning

  • Most standard residential applications in Melbourne take between four and nine months from lodgement to a council decision. Complex proposals involving heritage overlays, multiple objections, or referral authorities regularly take twelve months or more. VicSmart-eligible applications can be decided within 10 business days.

  • The Planning and Environment Act 1987 requires councils to decide on most applications within 60 statutory days. This clock is paused during advertising periods, RFI resolution periods, and referral authority processes. Real-world timelines are almost always longer than 60 days as a result.

  • Yes, for eligible applications. VicSmart is a statutory 10-business-day assessment pathway for lower-complexity applications. The critical qualification is eligibility: the application must fully comply with all relevant planning standards, and certain overlays will exclude a property from VicSmart regardless of the proposal's merits.

  • Outer growth corridor councils, Whittlesea, Melton, Wyndham, Casey, typically process standard residential applications more quickly than inner-city or inner-east councils. Boroondara and Stonnington are consistently among the slower councils for complex applications, partly because of higher Heritage Overlay coverage and more rigorous assessment processes.

  • The most common causes are incomplete documentation at lodgement, third-party objections requiring a council hearing, referral authority delays (VicRoads, Melbourne Water), complex overlays requiring specialist reports, and high council workload. Application completeness is the most controllable factor.

  • Yes. If council refuses a permit or grants it over objections, any party can appeal to the Victorian Civil and Administrative Tribunal. A VCAT hearing commonly adds six to twelve months to the overall timeline. Designing and documenting an application that minimises refusal risk and objection grounds is the best way to avoid VCAT.

  • For complex or sensitive applications, particularly those in Heritage Overlay areas or contentious neighbourhoods, a well-prepared pre-application meeting with council officers can reduce the risk of RFIs and surface issues before lodgement. For straightforward applications in low-risk zones, a pre-application meeting is often unnecessary.

  • Amendment VC288 (effective 16 October 2025) extended VicSmart eligibility to dual occupancy developments and two-lot subdivisions in most residential zones. Qualifying applications can now be decided in 10 business days with no public advertising, a significant reduction from the standard 4–9 month timeline. Eligibility requires full Clause 55 compliance and the absence of overlay exclusions including Heritage Overlays.

Want to Know How Long Your Project Will Take?

Planning timelines depend on your site, your council, and the quality of your application. There is no useful answer without knowing those specifics. Book a consultation with SilverPoint - Building Designers & Planning Consultants and get a straight, honest assessment of what your timeline realistically looks like and what we can do to improve it. SilverPoint Building Designer and Planning Consultant has been delivering planning permits across Melbourne for 40+ years and 1,800+ completed projects. We can tell you what's achievable, what's not, and what the process will actually involve.

Suburbs We Serve for Town Planning

We provide trusted town planning and building design consultancy across key Melbourne suburbs. Whether it’s a home extension, subdivision, or development planning, we’re here to assist.

  • Mulgrave
  • Ashburton
  • Keysborough
  • Clayton
  • Box Hill
  • Knoxfield
  • Dandenong
  • Box Hill South
  • Noble Park
  • Glen Waverley
  • Burwood
  • Vermont
  • Mount Waverley
  • Burwood East
  • Vermont South
  • Notting Hill
  • Chadstone
  • Wantirna
  • Springvale
  • Ferntree Gully
  • Wantirna South
  • Camberwell
  • Hawthorn
  • Hawthorn East
  • Kew
  • Balwyn
  • Balwyn North
  • Surrey Hills
  • Canterbury
  • Mont Albert
  • Mont Albert North
  • Richmond
  • South Yarra
  • Malvern
  • Malvern East
  • Armadale
  • Toorak
  • Prahran
  • Glen Iris
  • Ashwood
  • Doncaster
  • Doncaster East
  • Blackburn
  • Nunawading
  • Mitcham
  • Ringwood
  • Carnegie
  • Bentleigh East
  • Oakleigh
  • Hughesdale
  • Templestowe
  • Narre Warren
  • Berwick
Serving Melbourne & Nearby Suburbs

Proudly Associated With

Horizontal Member CMYK 1
HIA Member Loyalty Logo Years 10 1
BPC Full Colour Primary Logo 1
Logo
Rating Star (1)
Silver Point Pop Up Design

Book for a complimentary consultation

No pressure, no obligation - just straight, honest advice